Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effort involved in the different offshore activities in the same company during the same period. [Note: Onsite refers to work performed at the customer's premise and offshore refers to work performed at the developer's premise.]

If $50$ percent of the offshore work were to be carried out onsite, with the distribution of effort between the tasks remaining the same, the proportion of testing carried out offshore would be

  1. $40$ percent
  2. $30$ percent
  3. $50$ percent
  4. $70$ percent

Please log in or register to answer this question.

Position:
Show:

Related questions

0 0 votes
0 0 answers
1.7k
1.7k views
go_editor asked Apr 25, 2016
1,674 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
0 0 answers
1.6k
1.6k views
go_editor asked Apr 25, 2016
1,639 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
0 0 answers
1.3k
1.3k views
go_editor asked Apr 25, 2016
1,334 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
0 0 votes
1 1 answer
2.0k
2.0k views
go_editor asked Apr 25, 2016
1,954 views
Figure $1$ shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure $2$ shows the estimated and actual work effo...
1 1 vote
1 1 answer
3.0k
3.0k views
go_editor asked Apr 24, 2016
2,972 views
There are six companies, $1$ through $6.$ All of these companies use six operations, A through F. The following graph shows the distribution of efforts put in by each com...