1 1 vote Month Stage Cost(Rs. '000 per man-month) $1-2$ Specification $40$ $3-4$ Design $20$ $5-8$ Coding $10$ $9-10$ Testing $15$ $11-15$ Maintenance $10$ The number of people employed in each month is: Month $1$ $2$ $3$ $4$ $5$ $6$ $7$ $8$ $9$ $10$ $11$ $12$ $13$ $14$ $15$ No. of people employed $2$ $3$ $4$ $3$ $4$ $5$ $5$ $4$ $4$ $1$ $3$ $3$ $1$ $1$ $1$ With reference to the above question, what is the cost incurred in the new “Coding” stage? (Under the new technique, $4$ people work in the sixth month and $5$ in the eighth). Rs. $1,40,000$ Rs. $1,50,000$ Rs. $1,60,000$ Rs. $1,70,000$ Quantitative Aptitude cat1996 quantitative-aptitude tabular-data data-interpretation + – Misbah Ghaya 8.9k points 1.2k views answer comment Share Follow Print 0 reply Please log in or register to add a comment.